Ultra Fast Charge Points Greater than 100 kW and Up to 350 kW Output for Buses and HGV’s

The contracting entity procured multi (three) member frameworks for the supply and commissioning of EV Chargers of up to circa 350 kW capacity including associated equipment and services to be delivered in Ireland. These frameworks will not include installation of equipment. Lot 1: Ultra Fast Charge Points including greater than 100 Kw and up to 350 kW dedicated output to CCS and CHADEMO. Lot 3: Ultra Fast Charge Points greater than 100 Kw and up to 350 kW output for busses and HGV’s Delivery of charging equipment will be to locations in Ireland (Republic of Ireland and Northern Ireland) and commissioning may take place at any location in Ireland (Republic of Ireland and Northern Ireland).
CPV-Code: 34144900
Abgabefrist:
Typ: Contract award notice
Status: Not applicable
Aufgabe: Electricity
Vergabestelle:
name: Electricity Supply Board (ESB)
address: 2 Gateway, East Wall Road
postal_code:
city: Dublin 3 - IE
country: IE
email: None
phone: None
contact_point: Peter Coughlan
idate: 1. August 2020 03:38
udate: 1. August 2020 03:38
doc: 340511_2020.xml
authority_types:
activities:
Quelle: http://ted.europa.eu/udl?uri=TED:NOTICE:340511-2020:TEXT:EN:HTML
Unterlagen: None
Zuschlagskriterium: The most economic tender
Vertrag: Supplies
Prozedur: Negotiated procedure
Nuts: None
Veröffentlichung: 20.07.2020
Erfüllungsort: Dublin - IE
Link:
Lose:
Name Los Nr 1 None
Gewinner ABB Ltd
Datum
Wert None
Anzahl Angebote 1
Name Los Nr 2 None
Gewinner ABB Ltd
Datum
Wert None
Anzahl Angebote None
Name Los Nr 3 None
Gewinner ABB Ltd
Datum
Wert None
Anzahl Angebote None
Name Los Nr 4 None
Gewinner ABB Ltd
Datum
Wert None
Anzahl Angebote None
Name Los Nr 5 None
Gewinner ABB Ltd
Datum
Wert None